NEW BUILDING CONSTRUCTION STORY

On December 23, 2009, Providence Bible Church completed the construction of a new church facility on Greens Corner Road in Culpeper.  The Church Leadership carefully planned the new facility to provide a building that is sufficient for our current needs but with the capability to expand as our needs grow and as resources become available.  We were blessed with sufficient funds to permit us to construct this new building debt free.  What follows on this web page are the progress reports and pictures that were captured during the approximately one year construction phase for the facility. 

See the latest building floor plan
(Requires the Adobe Reader)

Latest Update is posted at the top


December 23, 2009 Update - Final Entry

On Tuesday, December 22, 2009, PBC was granted its Occupancy Permit (OP) after the completion of an inspection by Culpeper County.  The final outstanding item, the replacement of a valve in the sprinkler system, had been completed a couple days prior.  The snowy weather had delayed the inspection but it was God's timing for PBC to occupy its beautiful new facility.

No Pictures


December 16, 2009 Update

OUTSIDE: The final grading around the septic tank and approval by the zoning people on the temporary solution to the issues with the bio-pits are the only items remaining.  INSIDE: All carpeting has been placed and the wood grain flooring has been completed in the hallways.  The final coat of paint has been finished throughout the building and all that remains is touch up.  We are negotiating the carpeting on the portable stage area.  This was an extra per our contract.  The main gym floor and border has been placed and the lines for the courts will be done this week.  The new target date for securing our Occupancy Permit (OP) is now 12/18/09.  There is a very good chance that we could schedule a Christmas Eve service in the new building.  As soon as we get the OP, we will plan dates for our move.

No Pictures


December 9, 2009 Update

OUTSIDE: The main elements of the landscaping have been completed.  A lighted PBC sign is being fabricated and will be placed near the street.  Final grading in the back of the building will need to wait until we get some dry weather.  INSIDE: All carpeting has been placed and the wood grain flooring has been completed in the hallways.  All ceiling tiles have been placed.  The final coat of paint is now being applied in the Worship wing of the building.  The main gym floor has been placed and the blue border should be finished by Friday (12/11).  Our request for a temporary occupancy for the Worship wing of the building was denied by the County.  Their requirement is for us to get occupancy for the entire building.  We are still shooting for 12/14 as the date to get the occupancy permit (OP).  As soon as we get a date for the OP, we will plan dates for our move and for the first service in the new building (which now looks like it would be on January 10, 2010).

No Pictures


December 2, 2009 Update

OUTSIDE: All the paving is completed.  The main landscaping around the front and sides of the building is beautiful - including the islands in the parking lot.  More plants will be placed in the bio-pits as soon as we address the drainage problem that exists in them.  A lighted PBC sign is being fabricated which will be placed near the street.  Final grading in the back of the building will need to wait until we get some dry weather.  INSIDE: The HVAC units are all operational.  Flooring started yesterday, Wednesday, 12/2.  The final coat of paint will be applied as soon as the ceiling tiles have been installed and the flooring has been completed.  Ceiling grid has been completed throughout the building and placement of tiles is underway.  The countertops for the kitchen were installed yesterday.  We are now shooting for 12/14 as the date for an occupancy permit and to hold our first full service in the building the first week in January 2010.

11-29-09 DSCF0021-x.JPG (70670 bytes) 11-29-09 DSCF0059-x.JPG (75371 bytes) 11-29-09 DSCF0069-x.JPG (81820 bytes) 11-29-09 DSCF0087-x.JPG (77839 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 13.2 MB Power Point slide show file with 87 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - November 29, 2009


November 25, 2009 Update

OUTSIDE: All the paving is scheduled to be completed today (11/25) around noon. Since it needs to cure for at least 24 hours before handling traffic, no one will be allowed to drive on it until Friday.  The main landscaping around the front and side of the building is now finished, but there is still more to come at the entrance.  A lighted PBC sign is being fabricated which will be placed out near the road.  INSIDE:  The HVAC units are now operational.  Flooring will start on Monday, 11/30.  Painters have a lot of touch up to do (including adjusting the paint in the kitchen).  They plan to start the final coat when the ceiling tiles and flooring have been completed.  Ceiling grid work has been completed throughout the building (including the Worship Center) and tile placements are underway.  The countertops for the kitchen and bathroom will be delivered and installed on Friday.  With all factors taken into account, it now appears that we can shoot for 12/13/09 as our occupancy date, and probably have our first full service in the building the first week in January of 2010.

No Pictures


November 11, 2009 Update

OUTSIDE: If you have not gone to the new site to see the landscaping work, you are missing a treat. This week (weather permitting) nearly all the shrubs, flowers, and other plantings will be completed. All water, gas, and septic tanks will be buried.  “Bio pits” for water run off have been completed.  Preliminary parking lot grading work is finished and we are shooting to have asphalt placed by the 15th.  INSIDE: The painters have now completed the second coat of paint throughout the building. Ceiling grid work is up in the halls, offices, and class rooms and they started on the Worship Center.  The power is on and many lights have been placed in the new grid work.  Pray that the HVAC units come in by 11/13/09. The delay in their delivery is now causing day-to-day slips in the overall schedule.  Our new target date for occupancy is now 12/13/09.

11-04 IMG_2894-x.JPG (87192 bytes) 11-04 IMG_2895-x.JPG (103231 bytes) 11-04 IMG_2899-x.JPG (76779 bytes)
11-04 IMG_2900-x.JPG (56009 bytes) 11-04 IMG_2903-x.JPG (135252 bytes) 11-04 IMG_2905-x.JPG (85453 bytes)


November 8, 2009 Update

OUTSIDE:  One of the highlights of this past week was seeing the landscaping work begin – and it is awesome!  All of the sidewalks have been built and the water & gas tanks were buried.  “Bio pits” for water run off will be completed this week, as well as the septic tank installation.  Preliminary grading work is finished on the parking lots and we are hopeful to have asphalt placed by the 15th. INSIDE:  The painters have now completed the primer coat of paint through out the building and they are well on their way to finishing the second coat in the administrative wing and most of the classrooms.  Ceiling grid work is up in the halls, offices, and class rooms and they started on the Worship Center .  The power is on and lights are being placed in the new grid work.  Pray that the HVAC units come in over the next few days. They are now a critical path item that may cause a delay in our plans to occupy the building on 12/6/09.

No Pictures


November 1, 2009 Update

Praise Him for the way He continues to meet our every need regarding the new facilities. Nearly all of the primer coat of paint has been completed and the first round of “pointing up” has been done.  Ceiling grid work is well underway in the halls, offices, and class rooms on the Worship Center side of the building.  The power is on and lights are being placed in the new grid work.  Sidewalks have been completed.  Grading work has started on the parking lots and we are hopeful to have asphalt placed within the next two weeks.  Required “Bio pits” for water run off will be placed in the next few days, pending the weather.  Praise God that we are still on track to have all the requested work done within the financial commitments that the congregation approved back in February. We continue to shoot for a 12/6/09 occupancy date.

11-01 DSCF0234.JPG (73417 bytes) 11-01 DSCF0267.JPG (63929 bytes) 11-01 DSCF0288.JPG (83074 bytes)
11-01 DSCF0289.JPG (59762 bytes) 11-01 DSCF0296.JPG (48085 bytes) 11-01 DSCF0299.JPG (63105 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 17.6 MB Power Point slide show file with 56 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - November 1, 2009


October 21, 2009 Update

Painting of the primer coat started Tuesday (10/20).  Primary power was activated to the building and lights in the gym were turned on.  Drainage ditches were installed this past week to take roof water away from the building and the parking lot.  Sidewalks were started and will be finished on Thursday (10/22).  Flower beds were excavated and top soil was placed in them.  We continue to shoot for a 12/6/09 occupancy date.

No pictures


October 14, 2009 Update

God continues to meet our every need regarding the new facilities. Drywall work should be finished by Friday (10/16) and painting should start next week. The sound booth frame work was installed this week, and the basketball goals were delivered today.  Contracts have been secured for the flooring, ceiling tiles, kitchen appliances, cabinets, and counter tops.  Drainage ditches are being placed today and tomorrow to take roof water away from the building and the parking lot (to minimize ice build up in the winter).  Praise God that we are still on track to have all the requested work done within the financial commitments that the congregation approved back in February. We are shooting for a12/6/09 occupancy.

No Pictures


October 2, 2009 Update

Application of the stucco/EIFS finish on the front and the right side of the building should be finished this week (10/2/09).

2009-10-02 DSCF0178.JPG (71452 bytes) 2009-10-02 DSCF0181.JPG (66244 bytes) 2009-10-02 DSCF0183.JPG (73354 bytes)
2009-10-02 DSCF0185.JPG (66915 bytes) 2009-10-02 DSCF0186.JPG (56328 bytes) 2009-10-02 DSCF0192.JPG (64113 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 7.3 MB Power Point slide show file with 22 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - October 2, 2009


September 23, 2009 Update

Application of the stucco/EIFS finish on the front and the right side of the building is well under way.  The church steeple has been put in place atop the roof.  Inside, many walls have been hung with sheetrock on one or both sides as inspections are completed

2009-09-23 DSCF0183-x.JPG (72441 bytes) 2009-09-23 DSCF0192-x.JPG (63615 bytes) 2009-09-23 DSCF0198-x.JPG (69276 bytes)
2009-09-23 DSCF0200-x.JPG (70661 bytes) 2009-09-23 DSCF0207-x.JPG (50707 bytes) 2009-09-23 DSCF0214-x.JPG (71756 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 9.6 MB Power Point slide show file with 29 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - September 23, 2009


September 9, 2009 Update

Thank the Lord for His goodness as the outside of the building nears completion.  CECO has finished nearly all of their work, including trim and gutters.  With the completion of the block work, the crews can begin placement of the stucco/EIFS finish on the front and the left side of the building.

9-09 DSCF0036-x.JPG (72128 bytes) 9-09 DSCF0040-x.JPG (76097 bytes) 9-09 DSCF0046-x.JPG (77712 bytes)
9-09 DSCF0050-x.JPG (77302 bytes) 9-09 DSCF0058-x.JPG (75009 bytes) 9-09 DSCF0077-x.JPG (78957 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 17.1 MB Power Point slide show file with 53 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - September 9, 2009


September 2, 2009 Update

CECO has completed the roof and is working on the trim today.  Block work should be finished in the next week. Sprinkler system work should be finished in the next few days.  Placement of inside wall studs is finished, with the exception of the storage rooms being upgraded to classrooms.  Electrical work is also well underway.

No Pictures


August 15, 2009 Update

Placement of the inside wall studs is nearing completion and rough-in electrical work has started.  The replacement materials for the damaged roof sections has not yet arrived.

08-15 DSCF0036-x.JPG (80595 bytes) 08-15 DSCF0037-x.JPG (76851 bytes) 08-15 DSCF0038-x.JPG (80505 bytes)
08-15 DSCF0043-x.JPG (82306 bytes) 08-15 DSCF0046-x.JPG (72270 bytes) 08-15 DSCF0055-x.JPG (78598 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 6.6 MB Power Point slide show file with 20 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - August 15, 2009


July 31, 2009 Update

Lots of progress has been made in the last month.  The roofing is largely installed.  Much of the first layer of the exterior wall - with window cut-outs - has been installed -  and the metal studding for the interior rooms has begun.

Bldg Pix 7-31-09 - Picture 03-x.jpg (46946 bytes) Bldg Pix 7-31-09 - Picture 07-x.jpg (62514 bytes) Bldg Pix 7-31-09 - Picture 11-x.jpg (30241 bytes)
Bldg Pix 7-31-09 - Picture 16-x.jpg (65603 bytes) Bldg Pix 7-31-09 - Picture 18-x.jpg (56970 bytes) Bldg Pix 7-31-09 - Picture 28-x.jpg (65683 bytes)
Bldg Pix 7-31-09 - Picture 31-x.jpg (57851 bytes) Bldg Pix 7-31-09 - Picture 32-x.jpg (82958 bytes) Bldg Pix 7-31-09 - Picture 35-x.jpg (54421 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 16.9 MB Power Point slide show file with 52 pictures of the current building site progress. Select the slide show icon and the slides will automatically change every 5 seconds.

New Building - July 31, 2009


June 30, 2009 Update

The footers and the concrete slab are complete and all of the steel super structure is up and ready for the “standing seam” roofing to be installed. The siding and roofing materials should be delivered the week of July 5. You can begin to see the shape of specific features of the building.

DSCF0037-x.JPG (71207 bytes) DSCF0043-x.JPG (61187 bytes) DSCF0053-x.JPG (69229 bytes)
DSCF0054-x.JPG (73911 bytes) DSCF0056-x.JPG (82133 bytes) DSCF0058-x.JPG (76645 bytes)

If you have a high-speed (broadband) connection, click on the following link for a 11.3 MB Power Point slide show file with 35 pictures of the current building site progress.  Select the slide show icon and the slides will change every 6 seconds.

New Building - June 30, 2009


May 27, 2009 Update

Work has begun on the footers for the building The actual steel columns attach to the bolts that protrude from the large concrete pads. These will hold up the steel beams and girders for the roof and walls. The concrete footers will support the cinder block walls that will surround the concrete slab that is yet to be poured.

Picture 005-x.jpg (95452 bytes)

Picture 009-x.jpg (114801 bytes)

Picture 011-x.jpg (112975 bytes)

Picture 013-x.jpg (101969 bytes) Picture 028-x.jpg (94605 bytes) Picture 029-x.jpg (79822 bytes)


March 25, 2009 Update

The site work is complete and the pre-engineered building was ordered in early March. The building should be delivered on site in early May.  We are starting the process to obtain building permits for foundation plans now and will hopefully be pouring concrete footers in the near future. We are moving on schedule to complete the building in the Nov/Dec 2009 timeframe.

No Pictures, no changes at building site


February 22, 2009 Update

Site work is nearing completion. On February 22, 2009, the membership approved the final building plan and budget to construct a 26,000 ft2 building. The pre-engineered building will be ordered in March 2009. When completed later in the year, it will house a large worship center, classrooms, offices, and a fellowship area/gymnasium.

IMG_2663-x.JPG (69883 bytes) IMG_2664-x.JPG (77213 bytes) IMG_2665-x.JPG (92944 bytes)
  
Panoramic Pictures of Building Site
Bldg Site pano1.jpg (63171 bytes) Bldg Site pano2.jpg (99290 bytes) Bldg Site pano3.jpg (62152 bytes)


January 19, 2009 Update

Site work continues as dirt is being delivered and spread over the new pad site footprint, and the new road base is now being installed.

IMG_2633-x.JPG (72714 bytes) IMG_2634-x.JPG (72933 bytes) IMG_2636-x.JPG (98605 bytes)


December 6, 2008 Initial Report

PBC began serious work on the new church building on December 2, 2008.  In accord with the approved Land Disturbance Permits, trees and brush have been removed from the construction site and grading work has begun.
 

IMG_2446-x.JPG (96491 bytes)

IMG_2447-x.JPG (71049 bytes) IMG_2449-x.JPG (64653 bytes)
IMG_2450-x.JPG (76250 bytes) IMG_2451-x.JPG (88643 bytes) IMG_2452-x.JPG (83007 bytes)


 

 

Audio Sermons

Download Sermon Slides


 

Our Meeting Location


New Building Construction Story

 


Angel Food Ministries

 

Questions or problems with this website? - Contact:  webmaster@providencebible.org
© 2009 Providence Bible Church. All Rights Reserved 
Labeled with ICRA